History: Founded - 1913

As one of the largest and oldest electrical contractors in the United States, design-build, design assist construction and electrical contracting are the cornerstones of Fisk’s business.  Fisk prides itself on being able to deliver the best solutions to its customers by engaging every resource throughout the company in a controlled, focused process.  This process begins with providing key input into the budgeting and estimating of a project and extends throughout the life of the project during which formalized plans and schedules are blended with sophisticated project controls and experienced project management.  Fisk’s effective process allows it to successfully participate in any area of electrical contracting, be it design-build construction or service.  Fisk’s electric, security, and cabling expertise spans the commercial, industrial, governmental, high-rise residential, sports facility, casino and data center environments.  Whether high tech design-build construction or routine electrical or cabling services, Fisk has the resources and abilities to bring appropriate solutions to its customers whenever and wherever needed.  

In the early 1990’s, Fisk organized a dedicated team to focus exclusively on the installation and design of structured cabling systems.  Its customers welcomed this approach and Fisk Technologies soon evolved into a leader in each of its markets.  Today, many of those same customers that Fisk began servicing a decade ago continue to trust Fisk with their critical technology demands.  Always searching for ways to provide additional value, Fisk has further diversified and now offers Electronic Security, Audio-Visual, Networking, Telephony, Managed Services, and Wireless LAN/WAN services.  Fisk understands and appreciates the difficult challenges our customers face in balancing costs and value.  At Fisk, our goal is simple.  Earn business by providing superior value; retain it by providing exceptional service and becoming a long-term trusted partner.

Since its inception, Fisk has complemented its full-range electrical construction businesses with a “best in class” service and support organization as well as a twenty-four hours a day, seven days a week call center.  Designed to manage and support customers’ ongoing as well as emergency service needs, Fisk serves as a single point of contact for all electric, security, and cabling needs.  Any hour, any day, Fisk is proud to provide ready access to a team of highly qualified technical experts and professionals.

[Top]


Corporate Offices :

111 T.C. Jester Blvd.
Houston, Texas 77007
Phone: (713) 868-6111
Fax: (713) 880-2918

[Top]


Officers:

Chairman
Larry C. Brookshire

President and Chief Executive Officer
Kenneth J. Orlowski

President, Western Group
Darrell Harwood

Sr. Vice President, Eastern Group and Safety Officer
James S. Muhl

Sr. Vice President, Houston Group
Wayne McDonald

Sr. Vice President, General Counsel and Secretary
Gregory C. Thomas

Vice President and Chief Financial Officer
Lawrence J. McTague, III

Vice President, Client Relations
James E. Madget, PE

Larry Brookshire re-purchased Fisk on September 10, 2004.  Larry previously owned the company from 1996 through 2000.  Prior to that, Larry served as President and CEO of Dyna Electric Company for ten years. He has over 36 years of experience in the electrical contracting and construction industry.

Ken Orlowski joined Fisk in January of 2005 and currently serves as President and Chief Executive Officer.  Prior to joining Fisk, Ken served in executive officer positions in the legal and administrative areas of Delhi Gas Pipeline Corp., United States Steel Corp., and most recently as a Vice President with Marathon Oil Corporation.  He has over 35 years of experience in the legal, finance and corporate administrative areas.

Darrell Harwood began his career with Fisk in March of 1981 and has over 28 years of experience in the electrical construction industry.  During his years with Fisk, Darrell has served as a Project Manager, General Manager, Vice President and Regional Vice President.  Darrell currently serves as President, Western Group – Fisk Electric Company.

James Muhl began his career with Fisk in 1975.  He has over 32 years of experience in the electrical construction industry, including over 23 years of project management.  He currently serves as Senior Vice President, Eastern Group and Safety Officer– Fisk Electric Company.

Wayne McDonald began his career with Fisk in 1972.  He has over 35 years of electrical construction experience.  During his years with Fisk, Wayne has served an Estimator, Project Manager, Director of Engineering & Cost Control, Chief Estimator, Operations Manager, and Regional Vice President – Houston Contracts.  Wayne currently serves as Senior Vice President, Houston Group – Fisk Electric Company.

Greg Thomas joined Fisk in September 1997 and currently serves as Executive Vice President, General Counsel, and Corporate Secretary.  Greg has over 26 years experience as an attorney representing construction industry clients.   Prior to joining Fisk, Greg was General Counsel for a large general contractor.

Larry McTague joined Fisk in June of 2003 as Vice President and CFO.  Prior to joining Fisk, Larry was Vice President of Finance of Aker Kvaerner.  Larry is a CMA and has over 20 years of experience in the construction industry, including engineering and general contracting.

[Top]


Regional Division Offices:

Houston (1913)

111 T.C. Jester Blvd. (77007)
P. O. Box 4417 (77210-4417)
Phone: (713) 868-6111
Fax: (713) 868-5503

Wayne McDonald, Senior Vice President, Houston Group – Joined Fisk in 1972.

James Madget, PE, Vice President – 35 years industry experience. Joined Fisk in 2006.

Dallas (1956)

1617 W. Crosby Road, Suite 120
Carrollton, Texas 75006
Phone: (972) 466-0900
Fax: (972) 466-3988

Mike Dickman, Vice President – 35 years of industry experience. Joined Fisk in 1981.

Las Vegas (1989)

3451 West Martin Ave, Suite C
Las Vegas, Nevada 89103
Phone: (702) 435-5053
Fax: (702) 435-2127

Darrell Harwood, President, Western Group – 28 years of industry experience. Joined Fisk in 1981.

Miami (1997)

10125 NW 116th Way, #14
Medley, Florida 33178
Phone: (305) 884-5311
Fax: (305) 884-2192

Paul Maggi, General Manager – 36 years of industry experience. Joined Fisk in 1998.

New Orleans (1969)

181 James Drive West
Saint Rose, Louisiana 70087
Phone: (504) 889-0811
Fax: (504) 833-4045

Pat Clyne, General Manager 32 years of industry experience. Joined Fisk in 1998.

New York (2004)

341 W 38th Street, Eighth Floor
New York, NY 10018
Phone: (212) 823-9402
Fax: (212) 823-9401

Daniel L. Chapa, Vice President – Joined Fisk in 1996.

San Antonio (1969)

8964 Broadway
P.O. Box 17155
San Antonio, Texas 78217
Phone: (210) 828-3325
Fax: (210) 828-6434

Orvil Anthony, Vice President – 29 years of industry experience. Joined Fisk in 2003.

Austin (2007)

2013 Centimeter Circle
Suite B
Austin, Texas 78758
Phone: (512) 491-4100
Fax: (512) 835-6685

Orvil Anthony, Vice President – 29 years of industry experience. Joined Fisk in 2003.

[Top]


Contractor Associations:

  • N.E.C.A. (National Electrical Contractors Association)
  • F.E.C. (Federated Electrical Contractors)
  • A.G.C. (Associated General Contractors)

[Top]


In-House Facilities:

Fully Integrated Management Information System including Estimating, Purchasing, Accounting, Job Cost and Project Management, Quality Control Program and 3D CAD Drafting.  Microsoft Projects for Windows Scheduling Program.

[Top]


Dependability:

Fisk has completed every contract awarded.

[Top]


Safety Program:

  • Fisk has a written Safety Program.
  • Fisk has a written Drug and Alcohol Testing Program.
  • Fisk requires safety meetings for supervisors – quarterly.
  • Fisk requires Tool Box job site safety meetings – weekly.
    • Fisk supervisors conduct job site safety inspections – weekly.
  • Fisk’s Safety Department conducts unannounced job site safety inspections.

[Top]


Bonding Capacity:

  • Aggregate in excess of $500,000,000
  • Single Job Limit in excess of $100,000,000
  • Bonding Company’s BEST’S Rating:  A

[Top]


Work Categories:

Work Categories:

CSI Code

Electrical Construction

16050

Data / Telecommunications /
Fiber Optics Cabling

16740; 16700

Electrical & Electronic Instrumentation

16900

Pneumatic Instrumentation

15980

[Top]


Personnel:

Personnel:

 

Degreed Engineers

19

Project Managers

83

Estimators

25

LAN/WAN Specialist

12

RCDD Certified Specialists

5

General Superintendents

16

Foremen and General Foremen

307

Field (Hourly) Personnel

1,400 – 2,500

[Top]


Employment:

  • 2009 Average Employment – 3,137
  • Historical Peak Employment – 3,645
  • Most employees on a single project; 1,811 at peak, 885 average

[Top]


In-House Facilities:

Fully Integrated Management Information System including Estimating, Purchasing, Accounting, Job Cost and Project Management, Quality Control Program and 3D CAD Drafting.  Microsoft Projects for Windows Scheduling Program.

[Top]


Dependability:

Fisk has completed every contract awarded.

[Top]


Fisk Interstate Experience Modification Rate: (EMR):

 2009

2008

2007

0.73

0.72

0.71

Annual renewal date : September 30th

 

Fisk

2009

2008

2007

OSHA Recordable Incident Rate

2.59

3.31

3.25

(National Industry Average Standard is 8.10)

 

 

 

Fisk

2008

2007

2006

Lost Work Day Rate

0.55

0.94

1.13

(National Industry Average Standard is 4.80)

 

 

[Top]


Total Employee Hours Worked:

Year

Total

2009

6,098,011

2008

5,137,527

2007

4,246,161

 

 

 

 

 

 

 

[Top]